P R O G R E S S    O N    S I T E

The Saffron at Sentul East
Construction Progress
November 2006

 


Block A
1. Lift core wall form work : Level 12 to 13 in progress.
2. Beam and slab : Level 11 in progress.


Block B
1. Lift core wall form work : Level 12 to 13 completed.
2. Beam and slab : Level 11 in progress.


 


Block C
1. Lift core wall form work : Level 11 to 12 in progress.
2. Beam and slab : Level 9 in progress.

 


Block D
1. Lift core wall form work : Level 8 to 9 in progress.
2. Beam and slab : Level 7 in progress.

 


Podium Pool Deck
1. Level structure work in progress.
2. Underpinning works in progress.

Construction Progress
April 2008
January 2008
September 2007
October 2007
April 2007
November 2006