P R O G R E S S O N S I T E
|
The Saffron at Sentul East Construction Progress
October 2007
|
An aerial view of the project site.
|
|
|
A close view of Block A, B and C.
|
|
|
|
|
|
Block
A
Level 6 to 21
- Floor board : Level 6 to Level 21
completed
- Timber skirting : Level 9 to Level 21
completed
- Internal and external wall painting
completed
- Window glazing, sanitary ware
installation, plaster ceiling and door leaf installation completed
- Lockset installation in progress
|
Block
B
Level 6 to 21
- Floor board : Level 6 to Level 21 completed
- Timber skirting : Level 6 to Level 12 completed
- Internal and external painting completed
- Window and door glazing completed
- Sanitary ware installation completed
- Door leaf installation completed
|
Block C
Architectural Works
Level 5 to Level 28
- Floor board and timber skirting in progress
- Wall & floor tiling completed
- Internal wall painting : Finish coat in progress
- External wall painting completed
- Sanitary ware installation in progress
- Window and door glazing in progress
- Door leaf and lockset installation in progress
|
Block D
Architectural Works
Level 6 to Level 28
- Floor screed completed
- Wall & floor tiling completed (Level 5 in progress)
- Internal wall skim coating completed
- External wall plastering completed
- External wall painting : Under coat completed, base coat in progress
- Window glazing in progress
- Plaster ceiling in progress
- Installation of sanitary ware, door leaf and lockset in progress
|
Pool deck : Floor screed completed. Works on landscaping and swimming pool in progress.
|
Landscaping works at various sections of the pool deck is well underway.
|
Construction Progress
April 2008
January 2008
September 2007
October 2007
April 2007
November 2006
|