P R O G R E S S    O N    S I T E

The Saffron at Sentul East
Construction Progress
October 2007

 


An aerial view of the project site.

   


A close view of Block A, B and C.

   
   


 Block A
 Level 6 to 21

  • Floor board : Level 6 to Level 21 completed
  • Timber skirting : Level 9 to Level 21 completed
  • Internal and external wall painting completed
  • Window glazing, sanitary ware installation, plaster ceiling and door leaf installation completed
  • Lockset installation in progress


 Block B
 Level 6 to 21

  • Floor board : Level 6 to Level 21 completed
  • Timber skirting : Level 6 to Level 12 completed
  • Internal and external painting completed
  • Window and door glazing completed
  • Sanitary ware installation completed
  • Door leaf installation completed


 Block C
 Architectural Works
 Level 5 to Level 28

  • Floor board and timber skirting in progress
  • Wall & floor tiling completed
  • Internal wall painting : Finish coat in progress
  • External wall painting completed
  • Sanitary ware installation in progress
  • Window and door glazing in progress
  • Door leaf and lockset installation in progress


 Block D
 Architectural Works
 Level 6 to Level 28

  • Floor screed completed
  • Wall & floor tiling completed (Level 5 in progress)
  • Internal wall skim coating completed
  • External wall plastering completed
  • External wall painting : Under coat completed, base coat in progress
  • Window glazing in progress
  • Plaster ceiling in progress
  • Installation of sanitary ware, door leaf and lockset in progress


Pool deck : Floor screed completed. Works on landscaping and swimming pool in progress.


Landscaping works at various sections of the pool deck is well underway.

Construction Progress
April 2008
January 2008
September 2007
October 2007
April 2007
November 2006


Copyright @ 2012 YTL Land & Development Berhad (1116-M). All rights reserved.| Powered by YTL e-Solutions Berhad
Privacy Policy | Anti-Bribery & Corruption Policy | Code of Conduct & Business Ethics