P R O G R E S S O N S I T E
|
The Saffron at Sentul East Construction Progress
September 2007
|
An aerial view of the project site.
|
|
|
A close view of Block A, B and C.
|
|
|
|
|
|
Block
A
Level 6 to 21
- Floor board in progress from Level 10 to Level 26
- Floor screed completed
- Wall & floor tiling completed
- Internal skim coating completed
- External wall plastering completed
- Internal painting : Finish coat 80%completed
- External painting in progress
- Window glazing in progress
- Sanitary ware installation in progress
- Plaster ceiling completed
|
Block
B
Level 6 to 21
- Floor screed completed
- Wall & floor tiles completed
- Internal wall plaster completed
- Internal skim coating completed
- External wall plastering completed
- Internal painting : Finish coat in progress
- External painting completed
- Window glazing : 90% completed
- Sanitary ware installation : 90% completed
- Level 5 : Aluminium outer frame completed
- Plaster ceiling completed
|
Block C
Structural Works
- Typical floor completed
- Upper roof completed
Architectural Works
Level 5 to Level 28
- ALC block laying completed
- Floor screed completed
- Wall & floor tiling completed
- Internal wall plastering completed
- Internal skim coating completed
- External wall plastering : 95% completed
- External wall painting : Finish coat completed
- Aluminium outer frame completed
- Window glazing in progress
- Plaster ceiling : 80% completed
- Sanitary ware installation in progress
|
Block D
Structural Works
- Typical floor completed
- Upper roof completed
Architectural Works
Level 6 to Level 28
- Floor screed : Level 27 in progress
- Wall & floor tiling : Level 28 in progress
- Internal wall plastering : Level 28 in progress
- Internal wall skim coating : Level 28 in progress
- External wall plastering : 2nd stage in progress
- Aluminium outer frame : Level 28 in progress
- Window glazing in progress
- Plaster ceiling : Level 27 in progress
- Level 5 : ALC block completed
- Level 5 : Aluminium frame in progress
- Level 5 : Skim coating in progress
|
The pool deck is beginning to take final shape.
|
Landscaping works at various sections of the pool deck is well underway.
|
Construction Progress
April 2008
January 2008
September 2007
October 2007
April 2007
November 2006
|